Count working days to a deadline with NETWORKDAYS

The situation

Harbor Supply's operations manager plans warehouse projects in working days, because nobody is on site at the weekend. Subtracting one date from another gave calendar days, which overstated every project by the weekends it contained and made a three-week job look like a four-week one. The plan needs the count of days people will actually be working.

A1
fx
Count working days to a deadline with NETWORKDAYS — question sheet. Use the arrow keys to move between cells, Enter or F2 to edit, Escape to cancel, Control D to fill down from the cell above, and Control C and Control V to copy and paste.
Row numberABCDE
1ProjectStartDeadlineWorking days
2Dock resurfacingOct 5, 2026Oct 23, 2026
3Racking installOct 12, 2026Nov 6, 2026
4Audit prepOct 1, 2026Oct 15, 2026
5Fleet serviceOct 26, 2026Oct 30, 2026
6